Winton/590 S. Roadwork Starts Tonight

Source: NYS DOT
Source: NYS DOT
Set Text Size SmallSet Text Size MediumSet Text Size LargeSet Text Size X-Large
Share
Updated: 9/10/2012 7:38 am
Brighton, N.Y. - The traffic switch at the Winton/I-590 was postponed, and won’t begin until 9 p.m. Monday, September 10, during the overnight hours through Tuesday morning at 6 a.m.

On Tuesday morning, September 11, when the roads re-open, the new Diverging Diamond traffic pattern will be in place.

Winton Road will be closed between the north side of French Road and the south side of the Cambridge Place (the signalized intersections that are immediately south and north of I-590 interchange, respectively).

The entrance and exit ramps to and from the I-590 expressway (Exit 1) will also be closed.

Detours will be posted.

The construction schedule calls for road work to continue until October. Subsequent weekend closures are currently scheduled for the following dates, assuming weather allows:

• Friday evening, September 14 through Sunday, September 16

• Friday evening, September 21 through Sunday, September 23

For real-time travel information, call 511.
Share
National News
Authorities name casualties in Colorado fire
Bob and Barbara Schmidt dashed to their home on a dirt road in a heavily wooded area northeast of Colorado Springs as smoke from what would become the most destructive wildfire in Colorado history filled the air.

DapperDash

Inergize Digital This site is hosted and managed by Inergize Digital.
Mobile advertising for this site is available on Local Ad Buy.